If 12 workers build 12 tables in 12 days, how many days for 6 workers to build 6 tables (same rate)?
Answer
12 days
Explanation
12 workers make 12 tables in 12 days → 12 worker-days per table; (6\times?)=(6\times12) ⇒ 12 days.